KartridgPak Chub Machine Modernizations

KartridgPak Chub Machine Modernizations

Below you will find some of our most common modernization options for the majority of our KartridgPak Chub Machines. If you would like to discuss options available for your specific model, email us at info@rajones.com or complete and submit the form below and a modernization expert will contact you shortly.

ELECTRICAL CABINET REPLACEMENT:
This modernization replaces obsolete PLC, HMI and other electrical components to extend the life of the equipment, mitigate the risk of downtime associated with those older components, and for some models, add the ability to save recipes and add PLC controlled film registration.
LEAD TIME: 10-12 Weeks
INSTALLATION TIME: 3-4 Days
COST: $$$$

VARIABLE FREQUENCY DRIVE (VFD) UPGRADE:
This modernization replaces obsolete, hard to find and expensive DC Motors or Reeves drives utilized on main, film, and extruder (chemical emulson chub machines only) drives. This upgrade will improve production speed control with parts that are easier to source and less expensive.
LEAD TIME: 10-12 Weeks
INSTALLATION TIME: 1-2 Days
COST: $-$$

REMOTE TEACH PHOTOEYE REGISTRATION UPGRADE:
This modernization allows operators to adjust the film registration photoeye via the HMI instead of doing so by opening the main electrical cabinet. This upgrade mitigates the risks associated with opening and accessing the main electrical cabinet during production.
LEAD TIME: 10-12 Weeks
INSTALLATION TIME: 1-2 Days
COST: $

STAINLESS STEEL CLIPPING HEAD UPGRADE:
The stainless-steel clipping head is superior to the cast iron or aluminum versions installed on older equipment. It resists damage caused by repeated use and harsh cleaners. It is a more sanitary solution in washdown environments.  
LEAD TIME: 12-14 Weeks
INSTALLATION TIME: 1-2 Days
COST: $$$

GLUE VOIDER UPGRADE:
Only applicable on chub machines built for packaging glue/resin. This upgrade replaces gear driven rollers with belt driven technology. It also replaces the existing voider drive gearbox and includes a mechanical overload clutch. This addition protects the gear box from damage when package breaks occur, inhibiting voider rollers from turning.
LEAD TIME: 10-12 Weeks
INSTALLATION TIME: 1-2 Days
COST: $$$
 

If you would like to discuss what modernizations are available for your KatridgPak Chub Machine, please click the button below and complete/submit your request.